The completion date of a bridge replacement project in Apple Creek has been delayed because of some soil issues.  ODOT says the soil would not support the bridge’s foundation, meaning that the entire project had to be redesigned.  The bridge, which runs over Little Apple Creek on U.S. Route 250, is now scheduled to be finished sometime in December, although ODOT warns that weather conditions between now and then could push the completion date into next spring.